Construction Timeline Tracker: Barca at Godrej MSR City

Construction Timeline Tracker: Barca at Godrej MSR City


Construction timeline tracker for Barca at Godrej MSR City project updates and progress status

The construction timeline for Barca at Godrej MSR City is divided into clear phases, starting with earthwork and foundation in 2025 for Phase 1 and in 2026 for Phase 2. The super-structure, masonry, plastering, and joinery works follow in a systematic sequence, with finishing activities such as electrification, painting, fire safety fittings, and landscaping scheduled through 2030. Possession for Phase 1 is expected in 2030, while Phase 2 is targeted for early 2031. Each phase has a clear timeline, which helps in maintaining the pace of development while adhering to quality standards.

Phase 1 Construction Timeline (Barca)

The first phase of Barca consists of over 1,900 apartments spread across multiple towers. The construction is planned in well-defined stages.

Initial and Sub-Structure Work

  • Earthwork and leveling: April 1, 2025 – August 29, 2025
  • Foundation footing: August 29, 2025 – December 12, 2025
  • Upto plinth level: September 29, 2025 – March 12, 2026
  • Parking floor sub-structure: October 29, 2025 – July 10, 2026
  • Retaining wall: October 14, 2025 – April 11, 2026

Super-Structure Development

  • RCC/MS framed structure: March 13, 2026 – May 12, 2027
  • Masonry construction: July 11, 2026 – September 9, 2027
  • Plastering inside/outside: August 10, 2026 – October 9, 2027
  • Joinery (doors, windows, ventilators): November 8, 2026 – June 30, 2029
  • Water supply, sanitary, electrification (basic): August 25, 2026 – April 6, 2028
  • Flooring, tiles, dadoing: October 9, 2026 – November 2, 2028
  • Railing and grill fixing: August 25, 2026 – May 6, 2028

Finishing Works

  • Electrification and sanitary finishing: December 23, 2026 – December 27, 2029
  • Painting: January 22, 2027 – March 27, 2030
  • Fire prevention and firefighting fixtures: December 23, 2026 – December 27, 2029
  • Weatherproofing: September 9, 2026 – December 2, 2028
  • Elevation work: October 24, 2026 – August 29, 2029
  • Landscaping and external works: February 26, 2029 – March 31, 2030

Phase 2 Construction Timeline (Barca II)

The second phase, Barca II, adds another 600+ apartments to the township. Its construction is expected to begin in early 2026.

Initial and Sub-Structure Work

  • Earthwork and leveling: January 1, 2026 – May 31, 2026
  • Foundation footing: May 31, 2026 – September 13, 2026
  • Upto plinth level: July 1, 2026 – December 12, 2026
  • Parking floor sub-structure: July 31, 2026 – April 11, 2027
  • Retaining wall: July 16, 2026 – January 11, 2027

Super-Structure Development

  • RCC/MS framed structure: December 13, 2026 – February 11, 2028
  • Masonry construction: April 12, 2027 – June 10, 2028
  • Plastering inside/outside: May 12, 2027 – July 10, 2028
  • Joinery (doors, windows, ventilators): August 10, 2027 – April 1, 2030
  • Water supply, sanitary, electrification (basic): May 27, 2027 – January 6, 2029
  • Flooring, tiles, dadoing: July 11, 2027 – August 4, 2029
  • Railing and grill fixing: May 27, 2027 – February 5, 2029

Finishing Works

  • Electrification and sanitary finishing: September 24, 2027 – September 28, 2030
  • Painting: October 24, 2027 – December 25, 2030
  • Fire prevention and firefighting fixtures: September 24, 2027 – August 28, 2030
  • Weatherproofing: August 10, 2027 – September 3, 2029
  • Elevation work: July 26, 2027 – May 29, 2030
  • Landscaping and external works: November 26, 2029 – December 31, 2030

Key Milestones for Barca at Godrej MSR City

  • Phase 1 Pre-Launch Date: March 25, 2025
  • Phase 1 Launch: April 5, 2025
  • Phase 2 Launch: June 30, 2025
  • Possession Timeline: 2030 (Phase 1) | January 2031 (Phase 2)

The structured construction timeline of Barca at Godrej MSR City, Shettigere, Bangalore highlights the detailed planning that goes into delivering a large-scale township. Each stage has defined dates, ensuring accountability and steady progress from launch to possession. With its phased development approach, Barca is set to offer modern homes supported by strong infrastructure, making it one of the most anticipated projects in North Bangalore.

×